Responsibilities
Scope of services and responsibilities
4.1 Mobilization and work readiness
• Receive the approved and current contractual documents, approved contractor programme, method statements, temporary-works arrangements, material submittals, inspection and test plan, and required work permits. Verify that the documents needed to supervise each upcoming activity are available and authorized.
• Carry out a joint initial site visit with and contractor, record existing conditions, work fronts, structural elements, access restrictions, service interfaces, existing cracks and visible damage using numbered locations and baseline photographs.
• Confirm that the contractor has obtained the required approvals for work sequences, temporary supports, shoring, jacking, monitoring, excavation protection and high-risk procedures before the relevant works begin. This check concerns approval status and site applicability, not independent redesign or validation of calculations.
• Identify missing execution details, contradictions, or absent acceptance values, raise an RFI (Request for Information) and ensure that the affected operation remains on hold until an authorized written clarification is received.
• Prepare the site-supervision plan, inspection hold-point calendar, division of duties with the junior engineer and reporting templates.
4.2 Direct structural works supervision
• Maintain regular physical presence on the assigned site and personally attend designated hold-point operations. Junior engineer attendance does not substitute for the senior engineer’s presence at structural hold points.
• Inspect the location, geometry, workmanship, required supports and sequence of demolition and breakout, shoring/jacking and load transfer, temporary retrofitting arrangements, excavation and foundation formation, soil treatment, reinforcement and concrete works, concrete repairs, grouting and post-installed anchors, fabricated/erected steel, bolting and welding, coatings and structural fire protection, where scheduled.
• Compare executed work to the approved details, specifications, measurable tolerances, manufacturer-approved installation instructions and inspection/test requirements. No alternative technical criteria is introduced without formal approval.
• Check and document required jacking/shoring readings, monitoring triggers and release conditions stated in approved construction procedures, escalate unexpected movement, cracking or instability immediately.
• Withhold works for covering or subsequent work where mandatory inspections, tests or formal releases are incomplete. Confirm receipt of applicable authorization before load transfer, cutting structural reinforcement or removal of temporary supports.
4.3 Materials, QA/QC and test verification
• Check contractor material approvals and accompanying mill certificates, certificates of conformity, batch numbers, storage conditions, product validity, calibration status and approved trial mixes against the specifications.
• Apply and monitor the contractually approved ITP: inspect/witness designated activities, verify sampling frequencies, review independent laboratory findings and confirm that acceptance criteria are met before recommending acceptance.
• Cover concrete and repair strengths, reinforcement grades, compaction/lime-treatment results, anchor drilling and installation records, weld examinations, bolting requirements, coating thickness and fire-protection checks, as contractually applicable.
• Issue or recommend documented nonconformance records for deviations, establish corrective actions with the contractor and verify re-inspection, retesting and closure before recommending acceptance or payment.
• Ensure every test/inspection record is traceable to a material batch and identified element, location, pour, connection or work stage.
4.4 Site technical issues and controlled communication
• Identify ambiguous drawings, uncovered conditions, design discrepancies and clashes during construction, document them and submit formal RFIs through the designated communication channel.
• Implement only the formal written clarifications and revised documents issued or approved by contractually authorized parties. Do not prepare design calculations, select alternative strengthening solutions or authorize design changes.
• Assess site execution implications (work stoppage, sequencing, rework, affected quantities and program) of received instructions and advise the UNDP Project Manager, do not approve variations or added expenditure.
• Chair or participate in site coordination meetings as requested, issue factual action records and track open/closed technical matters.
4.5 Oversight of measurements, progress and reporting
• Assign daily field measurements and photo/document collection to the junior engineer. Check the completeness and reliability of their outputs, undertake independent sample checks and resolve discrepancies before endorsement.
• Apply the BoQ contractual measurement rules to accepted work.
• Reconcile contractor claimed quantities against approved drawings, inspected/accepted work, site measurement sheets and any formally authorized change, recommend justified quantities to the authorized UNDP contract administrator.
• Check contractor baseline and rolling schedules against site progress, identify delayed activities, failed tests, constraints, pending decisions and realistic recovery actions.
• Prepare signed weekly technical summaries and a monthly supervision package using the junior engineer’s underlying site records, including quantity verification, QA/QC logs, NCRs, photographic evidence and progress analysis.
4.6 Lead supervision team and coordination
• Provide daily technical directions to the junior engineer, approve the daily inspection allocation, measurement priorities and documentation system, review and sign off junior-prepared records requiring supervisory validation.
• Coordinate site activities with contractor personnel, laboratories, other discipline supervisors, hospital/DoH representatives and the UNDP team within the approved communication and decision-making arrangements.
• Maintain clear separation: the junior engineer collects/verifies routine facts, the senior engineer evaluates conformity, addresses technical nonconformities and submits formal recommendations, the contractor remains responsible for executing and testing the works.
4.7 Construction ESHS and structural safety
• Check contractor implementation of approved structural-safety controls for temporary stability, work at height, lifting, excavations, demolition, dust, noise, service isolation, exclusion zones and protection of patients/personnel where a hospital remains operational.
• Immediately report imminent structural hazards to the contractor and UNDP, request isolation/cessation of the affected operation and follow the site’s delegated stop-work/escalation procedure. Contractor HSE management remains the contractor’s responsibility.
• Ensure that unsafe, uninspected or materially nonconforming work is not recommended for acceptance.
4.8 Completion, defects and handover
• Lead inspections of completed structural items and prepare a location-based punch list, with remedial actions, evidence and closure signatures.
• Review contractor as-built records for correspondence with supervised execution, and verify completeness of test reports, material certificates, anchor/weld logs, coating records and final measured quantities.
• Recommend taking-over or technical completion only for work adequately supported by inspection/testing evidence, identifying residual deficiencies and pending contractual actions in a final report.
5. Inspections, records and reporting
Control Required procedure
Critical inspections Inspect before concealment, drilling/anchoring acceptance, reinforcement closure, concrete placement, controlled load transfer, removal of shores, and other approved ITP hold points. No evidence-based release = no recommendation to proceed.
Daily log Junior Engineer maintains a daily dated site diary and photograph index. Senior Engineer reviews daily and resolves/assigns material issues.
Inspection results Record location ID, drawing/revision, BoQ item, inspection date, required acceptance criterion, actual evidence, measured quantity, outcome and signatures.
Issue response Imminent safety risk: immediate notification and written record. Other material technical issues: notify authorized representatives within one working day, or sooner under contract.
Weekly reporting Senior Engineer issues concise progress, quality, constraints, look-ahead and action summary using verified junior Engineer records.
Monthly package Senior Engineer issues by fifth working day after each approved reporting month a signed supervision report and appendices, subject to contract adjustment.
Records retention Maintain editable logs plus signed PDFs, tested sample traceability, photographs, current revisions and an indexed evidence archive.